Year End Update

In 2020, we completed Phase I of the project!  The first stage of this project included paying all of the city permits and fees, trenching for utilities, running utility lines to the building site, upgrading water meter, changing from septic system to sewer, installing fire hydrant on site, improving driveway and sidewalks, excavating and grading foundation site and pouring concrete pad for the foundation of the building.  All of this is done and paid for.

The next phase starts soon!  This Spring, we hope to begin construction on Phase II of the Neighborhood Center.   This includes erecting the wood frame structure for the building, installing all doors and windows, installing shingle roof, installing all exterior siding and stucco and pouring concrete sidewalks around the building. At the end of this phase we will have a weatherproof shell for our building!